Construction Update

Building Your Vision

Follow the progress of Opal Village from ground to completion.

Project Timeline

Site Preparation

Q3 2024

Land cleared, infrastructure planning complete, groundwork commenced.

Foundation Works

Q4 2024

Foundations poured for all eight villas. Structural steel framework initiated.

Structural Works

Q1–Q2 2025

Above-ground structure rising. Concrete frames complete across all villas.

MEP & Finishing

Q3–Q4 2025

Mechanical, electrical and plumbing installation underway. Interior finishes commencing.

Completion & Handover

Q1–Q2 2026 — In Progress

Final inspections, landscaping and handover to owners.

Latest Updates

Final finishing works underway across all 8 villas
01

Final finishing works underway across all 8 villas

MEP installation and interior works progressing
02

MEP installation and interior works progressing

Full concrete frame completed — all 4 levels standing
03

Full concrete frame completed — all 4 levels standing

Exterior facade works in progress
04

Exterior facade works in progress

Interior fit-out commenced on schedule
05

Interior fit-out commenced on schedule

Pool excavation and waterproofing complete
06

Pool excavation and waterproofing complete

Above-ground structural works rising on all 8 plots
07

Above-ground structural works rising on all 8 plots

Structural steel and slab pour — Level 3
08

Structural steel and slab pour — Level 3

Level 2 column and beam structure complete
09

Level 2 column and beam structure complete

Ground floor slab and ground beam construction
10

Ground floor slab and ground beam construction

Foundation piling complete across all 8 plots
11

Foundation piling complete across all 8 plots

Substructure and drainage installation
12

Substructure and drainage installation

Site preparation and groundwork commenced
13

Site preparation and groundwork commenced

Tiling and surface finishes — bathrooms and kitchen
14

Tiling and surface finishes — bathrooms and kitchen

Electrical and data cabling first-fix complete
15

Electrical and data cabling first-fix complete

Pool tiling and filtration system installation
16

Pool tiling and filtration system installation

Landscaping and driveway works underway
17

Landscaping and driveway works underway

Near completion — final snagging in progress
18

Near completion — final snagging in progress