Construction Update
Building Your Vision
Follow the progress of Opal Village from ground to completion.
Project Timeline
Site Preparation
Q3 2024 ✓Land cleared, infrastructure planning complete, groundwork commenced.
Foundation Works
Q4 2024 ✓Foundations poured for all eight villas. Structural steel framework initiated.
Structural Works
Q1–Q2 2025 ✓Above-ground structure rising. Concrete frames complete across all villas.
MEP & Finishing
Q3–Q4 2025 ✓Mechanical, electrical and plumbing installation underway. Interior finishes commencing.
Completion & Handover
Q1–Q2 2026 — In ProgressFinal inspections, landscaping and handover to owners.
Latest Updates

Final finishing works underway across all 8 villas

MEP installation and interior works progressing

Full concrete frame completed — all 4 levels standing

Exterior facade works in progress

Interior fit-out commenced on schedule

Pool excavation and waterproofing complete

Above-ground structural works rising on all 8 plots

Structural steel and slab pour — Level 3

Level 2 column and beam structure complete

Ground floor slab and ground beam construction

Foundation piling complete across all 8 plots

Substructure and drainage installation

Site preparation and groundwork commenced

Tiling and surface finishes — bathrooms and kitchen

Electrical and data cabling first-fix complete

Pool tiling and filtration system installation

Landscaping and driveway works underway

Near completion — final snagging in progress