Opal Village
Construction

Construction Update

Building Your Vision

Follow the progress of Opal Village from ground to completion.

Project Timeline

Site Preparation

Q3 2024 ✓

Land cleared, infrastructure planning complete, groundwork commenced.

Foundation Works

Q4 2024 ✓

Foundations poured for all eight villas. Structural steel framework initiated.

Structural Works

Q1–Q2 2025 ✓

Above-ground structure rising. Concrete frames complete across all villas.

MEP & Finishing

Q3–Q4 2025 ✓

Mechanical, electrical and plumbing installation underway. Interior finishes commencing.

Completion & Handover

Q1–Q2 2026 — In Progress

Final inspections, landscaping and handover to owners.

Latest Updates

Final finishing works underway across all 8 villas
01

Final finishing works underway across all 8 villas

MEP installation and interior works progressing
02

MEP installation and interior works progressing

Full concrete frame completed — all 4 levels standing
03

Full concrete frame completed — all 4 levels standing

Exterior facade works in progress
04

Exterior facade works in progress

Interior fit-out commenced on schedule
05

Interior fit-out commenced on schedule

Pool excavation and waterproofing complete
06

Pool excavation and waterproofing complete

Above-ground structural works rising on all 8 plots
07

Above-ground structural works rising on all 8 plots

Structural steel and slab pour — Level 3
08

Structural steel and slab pour — Level 3

Level 2 column and beam structure complete
09

Level 2 column and beam structure complete

Ground floor slab and ground beam construction
10

Ground floor slab and ground beam construction

Foundation piling complete across all 8 plots
11

Foundation piling complete across all 8 plots

Substructure and drainage installation
12

Substructure and drainage installation

Site preparation and groundwork commenced
13

Site preparation and groundwork commenced

Tiling and surface finishes — bathrooms and kitchen
14

Tiling and surface finishes — bathrooms and kitchen

Electrical and data cabling first-fix complete
15

Electrical and data cabling first-fix complete

Pool tiling and filtration system installation
16

Pool tiling and filtration system installation

Landscaping and driveway works underway
17

Landscaping and driveway works underway

Near completion — final snagging in progress
18

Near completion — final snagging in progress

Chat with us