Construction

建设进度

见证您的愿景成真

从奠基到竣工,全程跟踪 Opal Village 的建设进展。

项目时间轴

场地准备

2024年第三季度

场地清理完毕,基础设施规划完成,土方工程启动。

基础工程

2024年第四季度

八栋别墅地基浇筑完成,钢结构框架开始安装。

主体结构

2025年第一至二季度

地上主体结构持续升高,所有别墅混凝土框架完工。

机电安装与精装修

2025年第三至四季度

水电暖通系统安装进行中,室内精装修工程启动。

竣工与交付

2026年第一至二季度 — In Progress

最终验收、景观绿化完工,正式向业主交付钥匙。

最新动态

Final finishing works underway across all 8 villas
01

Final finishing works underway across all 8 villas

MEP installation and interior works progressing
02

MEP installation and interior works progressing

Full concrete frame completed — all 4 levels standing
03

Full concrete frame completed — all 4 levels standing

Exterior facade works in progress
04

Exterior facade works in progress

Interior fit-out commenced on schedule
05

Interior fit-out commenced on schedule

Pool excavation and waterproofing complete
06

Pool excavation and waterproofing complete

Above-ground structural works rising on all 8 plots
07

Above-ground structural works rising on all 8 plots

Structural steel and slab pour — Level 3
08

Structural steel and slab pour — Level 3

Level 2 column and beam structure complete
09

Level 2 column and beam structure complete

Ground floor slab and ground beam construction
10

Ground floor slab and ground beam construction

Foundation piling complete across all 8 plots
11

Foundation piling complete across all 8 plots

Substructure and drainage installation
12

Substructure and drainage installation

Site preparation and groundwork commenced
13

Site preparation and groundwork commenced

Tiling and surface finishes — bathrooms and kitchen
14

Tiling and surface finishes — bathrooms and kitchen

Electrical and data cabling first-fix complete
15

Electrical and data cabling first-fix complete

Pool tiling and filtration system installation
16

Pool tiling and filtration system installation

Landscaping and driveway works underway
17

Landscaping and driveway works underway

Near completion — final snagging in progress
18

Near completion — final snagging in progress